Largest Adirondack solar project to date goes before APA

2022-09-17 00:47:48 By : Ms. Sunny Chen

The state’s first “build ready” solar project and the largest ever proposed in the Adirondack Park could get approval by the Adirondack Park Agency on Thursday.

It is a 20-megawatt electricity generation project – 62,235 solar panels able to power about 4,500 homes, erected over 111 acres of an old mine tailings pile in the town of Clifton in St. Lawrence County. The project is across the street from a former federal Superfund site where a million gallons of oil leached into the ground and Little River.

The APA has approved a 20-megawatt project before in 2021, but it was a slightly smaller scale with 46,000 panels on 100 acres in the Town of Ticonderoga.

The New York State Energy Research and Development Authority (NYSERDA) is seeking permit approval for a major public utility use from APA commissioners. The project is proposed in one of the rare industrially zoned areas of the park. It is also near National Grid’s Star Lake substation, though about 78,000 linear feet of underground connector lines and conduit would need to be installed to make the hook up.

APA staff have recommended the project be approved with conditions.

NYSERDA’s “build ready” program prioritizes renewable energy projects on commercial sites, brownfields, landfills, former industrial sites and other underutilized areas that are also in proximity to the electric grid. Former Gov. Andrew Cuomo first announced the 20-megawatt array in April 2021 and called it “the innovative thinking that we need to put into action in order to compete in a green energy economy.” At the time of the announcement, the APA was still reviewing its regulatory role.

Now, according to the APA draft permit, the agency is reviewing the project as a major public utility use in industrial use and resource management lands. It would be a subdivision in a resource management area and a new land use on resource management lands within 1/8th mile of tracts of forest preserve classified wilderness. It would fall within 300 feet of the edge of right-of-way of state highways in the park. Conditions agency staff recommend requiring  include decommissioning plans, compliance with wetlands regulations, erosion and sediment control plans, examples of activities that would need further APA authorization and other stipulations.

The land is owned by Benson Mines, an iron-ore mine that closed in the 1970s after nearly a century of operation. The mine was once owned by J&L Steel Corp. and in the 1950s was considered “the largest open pit magnetite mine in the world and employed up to 1,000 people,” according to the U.S. Environmental Protection Agency. A portion of the J&L Steel. land became a federal Superfund site in 2013 because  a plume of more than 1 million gallons of No. 2 fuel oil was seeping into Little River, a tributary of the Oswagatchie River.

A spokesperson for NYSERDA said the tailings pile where the solar panels are proposed is not part of an enforced EPA Superfund cleanup.

The DEC said that the petroleum polluted site is across the street from the mine. DEC and EPA “conducted extensive remedial efforts” for decades, but DEC has recently assumed management of the site under the state’s spills program. Responsibilities include “collection and disposal of thousands of gallons of free product collected annually as part of ongoing monitoring.”

Stuart Carlisle, director of the mine, told the Adirondack Explorer in April 2021 that he does some timber harvesting on his property now, and works with a contractor to sell aggregate to construction companies. The tailings pile, Carlisle had said, is mostly crushed stone with a sandy consistency.

Peter Bauer, executive director of Protect the Adirondacks, has visited the proposed site and believes it is the right place for renewable energy installations.

“It’s a landscape like the moon in places,” Bauer said. “It’s just ripped up, sandy, sandy earth, scrub vegetation. It’s really weird because it’s surrounded by forest.”

David Gibson, managing partner of Adirondack Wild: Friends of the Forest Preserve, said the site makes sense for the project, but he had concerns about the five acres of tree-cutting included in NYSERDA’s application. He believes NYSERDA should compensate for the loss of mature trees by planting trees elsewhere.

Bauer said the solar array was worth it, considering the state’s climate emissions reduction goals. The Adirondack Council also said it is in support.

Gibson had questions about the completion of the Superfund cleanup work, and blamed the APA’s “poor practice” of using a checklist on its application rather than its past “findings of fact” method. The checklist, Gibson said, does not offer the public and commissioners awareness of the site’s history. 

“DEC’s ongoing site management activities at the site would not have an impact on the potential solar development, and DEC looks forward to the beneficial reuse of this large industrial area,” the department said.

NYSERDA’s application materials, which the Explorer received through a Freedom of Information Law request, was over 6,000 pages. The documents included plans for solar development, stormwater pollution discharge, snow management, visual impact assessment and decommissioning plus a glare analysis, logs and charts from test boring into the area’s soils and a lease agreement between NYSERDA and Benson Mines.

According to the April 6, 2021 lease, NYSERDA will pay Benson Mines a fee of $24,549. It will also pay $1,000 per acre or partial acre per year, with an increase of 2% annually on the anniversary of the effective date. The lease states the premises is about 244.49 acres, which would cost about $245,000 a year. NYSERDA could assign the lease and obligations to a limited liability company it formed called BR Project 1. 

APA staff member Ariel Lynch asked NYSERDA the purpose of the LLC, records show. Tracy Darougar, project manager for NYSERDA’s build-ready program, responded that the corporation “is the vehicle by which NYSERDA obtains development rights,” and that when the state selects a solar developer, “we transfer the LLC membership interest to the developer as opposed to all the individual development rights.”

A NYSERDA spokesperson wrote it intends to transfer its membership interest via a public auction. NYSERDA hopes construction will start between 2023 and 2024, with electricity flowing to the grid by November 2024.

A spokesperson for NYSERDA said it is submitting local permitting applications to the town and St. Lawrence County for approvals this month. The New York Independent System Operator, a group that ensures power system reliability, is doing an interconnection analysis. NYSERDA also needs permits for  building, road crossing, state pollutant discharge and construction discharges. 

It is not yet clear how the Town of Clifton may benefit from the project. NYSERDA said it cannot comment on potential payment in lieu of taxes agreements as discussions are ongoing. A spokesperson said there will be economic benefits to the community through construction, operation and maintenance jobs, lease payments to landowners and tax payments to communities. NYSERDA is also looking at the financial feasibility of electric vehicle charging stations in the town.

Clifton Supervisor Charles Hooven said there have been early discussions with NYSERDA about potential benefits, but he doesn’t expect anything until there is a solar investor ready. He’s excited to see something happening at the site, where prior proposals failed. Some in town believe the mine will reopen again, he said. 

“It existed for so long,” Hooven said. He did not think that would happen, and said he was keeping an open mind to solar development.

The U.S. Fish and Wildlife Service wrote that there were no threatened or endangered species or critical habitats on the property. The DEC found the land does support a population of pink shinleaf, a threatened flowering plant in New York. There are also wetlands on the site and one intermittent stream.

The solar array is not expected to cause any negative visual impacts within a 5-mile radius. An environmental engineering firm NYSERDA hired said considering the industrial surroundings, “the project will not impact the overall importance or character of the park.”

A NYSERDA spokesperson also confirmed a portion of a local snowmobile trail has been rerouted to accommodate the solar project. He said small portions of the route were moved slightly east, though it will continue to connect the northern Junction 40 to the southern Junction 15 as it traverses Benson Mines land.

Correction: This story has been updated to correct a previous version, which said the Benson Mines solar project was the largest approved in the park. The APA approved a 20-megawatt solar project in Ticonderoga in 2021. It has also been updated to clarify that the solar project will not be visible from any public locations.

Sign up for Gwen’s weekly “Adirondack Report” newsletter

Or click here to see the full slate of daily and weekly newsletters

Tags: adirondack park agency, Benson Mines, solar

Gwen covers environmental policy in the Adirondacks. Contact her at (518) 524-2902 or gwen@adirondackexplorer.org. You can also follow her on Twitter, @gwendolynnn1. Sign up for Gwen’s newsletter

What else should we do with a Superfund site that is not usable for schools or housing ? A solar array that will produce a large amount of electricity is perfect for the site. I hope the APA agrees.

Leave the solar panels out pf the adirondacks, its beautiful as it is now,putting in solarpanels would take away the beauty. And when one takes pictures and they are in the photo it will look tacky. Dont destroy the beautiful adirondacks to ugly solar panels.

Who gets the electricity? Will it stay in the Clifton, Fine area? If not then I hope it can turn into a manufacturing site that supply jobs. If Peter Bauer and David Gibson approve the project then that should be a red flag to the people of the Adirondacks that the project is a sham

I am not a fan of large-scale wind or solar power generation within the Park. Abandoned mines, industrial areas, and Superfund sites need to be returned to a non-toxic natural state. I also feel adding additional 78k feet (14 miles) of transmission lines is not inconsequential, whether buried or not. Environmental engineering studies conducted by NYSERDA need to be corroborated independently. Large solar arrays are not benign entities to wildlife.

While I see the reasoning behind finding an alternate use for an environmentally damaged industrial area, should the emphasis be on simply creating more energy likely be shipped out of the area? I would almost rather see the mine operating again – something that could perhaps help support the community directly with jobs. Isn’t that the idea of “industrial” areas within the Park – to support communities rather than downstate energy demands? We generate hydro energy already, and could generate even more with smart dam overhauls to better support aquatic life. To me, that is a better fit for the Park and its residents – especially if we keep the power within the Park. We should not be encouraging downstate energy use by using the Park as a wind/solar/hydro power reservoir. Let the mega-users produce their power in THEIR backyards, and cut down on building more and more long-distance transmission lines through sensitive habitat.

Your email address will not be published. Required fields are marked *

Notify me of new posts by email.

The Adirondack Council’s annual State of the Park report is out now, highlighting the threats and challenges, and the hopeful and optimistic things that have affected the Adirondack Park over the past year..…Read more.

36 Church St. Saranac Lake, NY 12983 Phone: (518) 891-9352

Copyright © 2022 · Adirondack Explorer All Rights Reserved Web Services & Search Engine Optimization By: Suloff Designs

sign up for news updates from the Adirondack Explorer!